Weekly report : from February 26th to March 5th, 2004

3/8/2004
Press release

Treatment activity:
During this period, the Establishment treated 4 tons of spent fuel assemblies.the UP2 800  factory continued the maintenance actions of the installations.
From all treated assemblies, a total of 243 tons have been processed to date this year.
During this period, 18 canisters of vitrified fission products have been produced(1).
Since the beginning of the year, 103 canisters have been produced.
It should be noted that the facility of hulls compaction (ACC) produced 10 canisters of compacted residues.
Since the beginning of the year, 201 canisters have been produced.


Shipment activity :
One shipment of 2 casks( TN17) of spent fuel assemblies from Borssele nuclear power plant  (Netherland)  arrived at the Valognes railway terminal on the March 5th at 9h15 pm.


(1)The fission products (ultimate residues of spent fuel) are incorporated in heated glass to approximately 1100°C. The whole is poured in stainless steel containers. The fission products are an integral part of stable, compact and resistant glass. This process is called vitrification.


More about
AREVA is a worldwide expert in the energy field, with a strong industrial presence in over 40 countries. The Group provides its customers with technological solutions for nuclear energy production and electricity. AREVA also offers interconnect systems, principally in the telecommunications, computer and automotive markets. The 75,000 AREVA employees are thus committed to the major challenges of the 21st century: access to energy for everyone, preservation of the planet and responsibility toward future generations.