Weekly report : from December 13 through December 19 2001

12/20/2001
Press release

UP2 plant :
At the UP2 plant, shearing of fuel assemblies from a batch of 900 MWe EDF fuel is in progress in the R1 head-end facility. A total of 718 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, line B is in service. Lines A and C are on standby. A total of 454 canisters of glass have been produced to date this year.

UP3 plant :
At the UP3 plant, shearing of fuel assemblies from a batch of 900 MWe EDF fuel is in progress in the T1 head-end facility. A total of 196 metric tons of uranium have been processed to date this year.
At the T7 vitrification facility, lines A, B and C are on standby. A total of 254 canisters of glass have been produced to date this year.