Weekly report : from July 13 through July 19, 2000

7/20/2000
Press release

At the UP2 plant,  R1 head-end facility is on a shutdown period for maintenance. A total of 452 metric tons of uranium have been processed to date this year.

At the R7 vitrification facility, line B is in service, lines A and C are on standby. A total of 234 canisters of glass have been produced to date this year.

At the UP3 plant, T1 head-end facility is on a shutdown period for maintenance. A total of 231 metric tons of uranium have been processed to date this year.

At the T7 vitrification facility, line C is in service, lines A and B are on standby. A total of 152 canisters of glass have been produced to date this year.