Weekly report : from July 4, 2002 through July 10, 2002

7/11/2002
Press release

Treatment activity :
Head-end facilities are on a shutdown period for maintenance.

Shipment activity :
A shipment containing three casks of 36 spent fuel assemblies coming from german power plant of Gröhnde and Phillipsburg (PWR 1300 MWe) arrived at the railway terminal of Valognes.

The actuality, it is also... Works of disassembling, in the zone of marling, of the old pipe of liquid releases are in progress accordance with the program.
The results of analyses of the samples performed in accordance with the specific programme of monitoring of the environment of the site are all lower than 1 Bq/g.